EEPCo  |  Project Financer  |   Raised Issues  |  Public Consultation  |  Visitors   |  Organization Structure

Home
Brief
Progress
Gallery
Event
FAQ


Web Counter
  Hit Counter

Currently, 45.96 percent of the overall Project is completed as of July 3, 2011

Camps and Site logistic Installation works

Camps for Employer/ Employer Representative, Contractors Expatriate camps and local staff's camps are completed.

Air strip, Clinics, canteens, bars and other social service centers for the staffs are completed.

Site logistic installations such as workshops laboratories, stores, batching plants, crushing plants and other important equipments are in place.

River Diversion Works

 

 

Diversion Tunnels

Excavation and lining works of the three diversion tunnels are completed and the dry season flow of Omo River is diverted through the center tunnel on January 20, 2009.

At present, the Omo River flow passes through the three diversion tunnels and the area of the dam foundation and powerhouse is fee of water..

Cofferdams

The concrete wall of the D/S cofferdam has been 100% completed and the rock fill work is 78.5% completed, the contractor has completed installing first and second phase geo-membrane and is preparing to install third phase

RCC Dam Construction

Dam abutment excavation is 100% completed.

Power House

Power house area excavation is in progress. Excavation volume has been  increased due to shift of PH. As a result 87% of the excavation work is completed relative to the new total area of excavation

Power Waterways

 

Power Intake

•The position of the Intake is shifted 250 m left side and 320m right side towards u/s. The quantity of excavation at the new location is estimated to be 227,000 m3. Out of this volume 174,790 m3 is excavated so far. The progress of the work is 81% according to the new volume.

Power Tunnels

•  To date the left and right Power Tunnels excavations are approximately 83% and 73.4% completed respectively

Manifolds

Excavation of Branches of the Left and right Manifolds is completed, installation of support structures and wire mesh and shotcrete activities are completed.

 

Laboratory Works

Second phase of RCC trial mix tests for the main dam is in progress.

RCC trail mix tests on different types and brands of cement are in progress. According to the results Pozolana Portland Cement (PPC) is found to be the best type of cement for RCC Dam construction.

Roads & Bridges

 

About 135 km long access roads inside the site are constructed.

The Omo downstream Permanent bridge work is 100 % completed and it was opened for Light vehicles traffic on Sep 06, 2009 .

The request for approval of reduction of the right of way of the road from 30 to 20 m is approved by Ethiopian Roads Authority (ERA) in order to reduce the impact of the road. Currently, the consultants has completed the rechecking of the impacts in the 20m corridor and submitted the review of the final resettlement and compensation plan.

Hydromechanical and Electromechanical works

  • Contract for the Electro mechanical and Hydro mechanical works have been signed on May 12, 2010 with DEC (Dongfang Electric International Corporation) of China at a cost of USD 340,727,870 plus ETB 486,627,544 and USD 105,227,709 plus ETB 150,919,919 respectively. The total contract price for the Electro mechanical and Hydro mechanical works in USD is 495,506,200.
  • A tripartite agreement has been made on July15, 2010 among EEPCo, Salini (EPC Contractor) and DEC (Plant Contractor).
  • The contracts for EM and HSS Works are effective as of July 15, 2010.
  • With respect to the submitted drawings/documents, DEC accomplished 28% and 35% design for EM and HSS works respectively.

So far 380 design drawings/documents have been submitted by DEC for review and approval; of the submitted design drawings/document:

    • 262 documents(about 69%) are Returned for Correction(RFC)
    • 54 documents( about 14%) are approved
    • 64 documents under review (about 17%)
  • The manufacturing works of the components of EM and HSS equipments are under progress.
  • The third technical coordination meeting has been conducted from May 23rd to 27th/2011 in Addis Ababa. The meeting has been attended by the representatives of EEPCo, ER, Salini (EPC contractor) and DEC (Plant Contractor).
  • Great emphasis has been given to speed up the design of EM and HSS equipment of the project and ensure the interfacing activities with that of the civil works.
  • In order to speed up the design works, establishment of a team drawn from EEPCo, ER, and EPC contractor is under process. The team will closely work with DEC’s engineers in Chengdu, China.
  • Considering the delays in design of EM & HSS works, EEPCo requested the DEC’s top management support and intervention in order to speed up and ensure the completion of the project as scheduled.
  • As no satisfactory improvement is obtained from DEC’s side, EEPCo invited DEC’s higher level management for a coordination meeting scheduled for first week of July 2011.
  • In the managerial coordination meeting, it is planned to discuss on the performance of DEC’s design activities and general coordination of the works and to find out all possible resolution.

Transmission Line

(GIII To Wolaita-Sodo Substation)

  • Gibe III-Wolaita Transmission Line (50.3 km double circuit 400kV, 3 phases and 51km single circuit 400kV) Construction Contract has been signed on July 24, 2009 with TBEA of China at a cost of USD 34 M of which 85% is to be covered by a loan from EXIM Bank of China.
  • TBEA Co.Ltd has submitted additional design documents/drawings to EEPCo for approval. The submitted documents/drawings are approved by EEPCo’s Transmission and Substation Engineering Office.
  • The contractor is preparing design for foundation.
  • The Loan Agreement for execution of the Gibe III-Wolaita-Addis Ababa 400kV Power Transmission Project (comprises substations and transmission lines) has been signed by MoFED and by EXIM Bank of China. The Loan Agreement has been also approved by the Council of Ministers and has been deliberated to the Ethiopian Parliament for its ratification. After review by Budget and Finance Standing Committee, the Parliament has approved the Loan Agreement on June 16, 2011.
  • For implementation of the project the Contractor has submitted the work schedule.
  • EEPCo’s delegates are attending tower test witnessing in China since June 6, 2011.
Environmental And Social Studies

•  Establishment of the Environmental and Social monitoring and Management Implementation Unit in Addis Ababa, at site and at Jinka has been completed.

• Four Environmental and Social monitoring Coordinators have been assigned at four woredas around Jinka (Dasenech,Nyagatom,Hammer and Selamago).They are mainly engaged in awareness creation works.

• All ESIA related studies are completed. All the final ESIA and RAP reports are posted on EEPCo's Website as of March 5, 2009. Final report for archeological study has been submitted. The establishment of an office for the Environmental and Social monitoring and management sub process team at project level is completed. Preparation of project- based website is Completed. A mediation between the African Development Bank and Friends of Lake Turkana (FOLT) has been conducted on June 10 and 11, 2009, in Nairobi and the AfDB representatives have briefed EEPCo's management on the outcome. The FOLT has requested the bank for further studies to be conducted on the project, especially hydrological studies and public consultation on the Kenyan side. The Bank has accepted the request and engaged in finding consultants for the study.

• The first meeting of the Environmental Advisory panel has been held on 10 july 2008 and the members have received electronic copies of the ESIA studies documents. The Advisory panel members have conducted the first site visit from 31 st July 2009 to 02 August 2009 and held a meeting during the site visit. The EAP has been conducting a number of meetings and has prepared action plan for the Panel.

•  Establishment of the Environmental and Social monitoring and Management Implementation Unit in Addis Ababa, at site and at Jinka Town(SNNP).

• Additional Public consultation has been done on December 2009 to February 2010 with upstream and downstream communities.


General

A joint mission from the AfDB, EIB and World Bank were in Ethiopia from October 10-20, 2009. The missions had visited the project site and consult the downstream communities. The missions also held different meetings with EEPCo and participated in the EFTA study Workshop conducted on oct-19-2009.


Plung Pool

The Contractor stopped the works waiting for the results of the hydraulic model test related to the depth of the invert of the plunge pool. In addition the quality of the rock is not good and the Contractor is waiting a new support design.


Chida-Sodo Road And Employer’s permanent camp

•  On the left side of the river, the Contractor is doing clearing and levelling works of the road, so far 26.5 km has been done.

•  on the right side of the river, the clearing and levelling works has been done up to a distance of 4km, The Contractor stopped the work on the right side as he has shifted the resources to the left side

•  The Contractor has completed earth works and he is preparing a platform to commence the construction of the Employer's permanent camp

•  The Contractor has commenced construction of EPC plant contractor's (DEC) camp.

 

Compensation Payments

•  So far Compensation payment for the permanent camp area has been made for fifty three (53) peoples with a total of 3.87 Million Birr.

In total one hundred and sixty three (169) persons are compensated so far for Sodo-Chida road relocation and Employer's permanent camp with Birr 7.52M.






 

Copyright © 2009 Gibe3 Hydroelectric Project

News and Events



"Gibe III won’t affect Kenya: Ambassador"

The Ethiopian Herald on its issue on December 16, 2011 posted an interview with The Kenyan Ambassador in Ethiopia Dr. Monica Juma.

Read More ...

"Life is better with Trees"
Tree Planting Day around Gibe III Project (July 24, 2011)

As part of promoting environmental protection, the Environmental and Social Monitoring and
Management Sub-Process team of EEPCo in collaboration with the Health, Safety and
Environment (HSE) section of the EPC contractor and the camp manager, organized a tree
planting occasion on July 24, 2011.

Read More ...

Launch: RCC Dam Concreting
Works

The Gibe III Hydroelectric Project's Site Office
announced that the Dental Concreting work of
the Roller Compacted Concrete (RCC) Dam
foundation, has been officially commenced on
August 19, 2011.

Read More ...

Pastoral community Representatives Visit to GibeIII Dam Construction Site

Lokomori Lotolien, 43, of Dassenech ethic groups seems to scrutinize things restlessly as he is responsible to convey all the information he gathered about Gibe III Dam construction, and the other operational Dams (Gilgel Gibe I and II) to the community who delegates him to investigate the impacts of those Dam on flows of the Omo River.

Read More ...

“We had great enthusiasm to visit this giant Project “

Luckily, the Gibe III Hydroelectric Project has called the attention of many visitors since its infant stage. From the high level government officials to various academic and media institutions have paid attentive visits frequently.

Read More ...

A Report of the ESAP (Environmental and Social Advisory Panel) of Gibe III Hydroelectric Project on First Site Visit

The Gibe III Hydroelectric Project is now under construction phase when operational it is expected to produce 1870 MW. Currently Salini COSTRUTTORI S.p.A on behalf of EEPCo is undertaking construction of this project.

Read More ...

Gibe III Today (News Letter 2)

High-ranking government officials expressed their impression regarding the progress of work on the Gibe III Hydroelectric Project and the united efforts of its staff.

Read More ...

Gibe III Today (News Letter 1)

The African De v e l o pme n t Bank (AfDB) and the World Bank (WB) experts acknowledged Gibe III h y d roe l e c t r i c project is the best option in the power sector developments, and would boost the economic and social integrations among the Eastern African countries

Read More ...

GIBE DAM III - Pride of Ethiopia!

Gibe Dam III is indeed the Pride of Ethiopia! Once completed this project will generate 1870 Mega Watt electric power. Currently Ethiopia has only ~ 800 Mega Watt and Gibe III will boost the output by 230%! This project provides thousands of job opportunities for the local communities.

Read More ...

Letter to the Editor By Azeb Asnake, Gibe III Hydroelectric Project Manager1

We appreciate for her “Greens must have very hard hearts if they can look at flood-hit Ethiopia and still say ‘don’t build dams” article posted on www.spiked-online.com. Rothschild has exactly reflected the facts of the Gibe III Hydroelectric Project. Thank you, Rothschild.

Read More ...

Ethiopia - They don’t give a dam about development Greens must have very hard hearts if they can look at flood-hit Ethiopia and still say ‘don’t build dams’.

Recently a group of international NGOs has been leading a campaign to stop the building of the Gibe III hydroelectric dam in Ethiopia. They say the dam will disrupt the local ecosystem and the traditional ...

Read More ...

2003 E.C . New Year Best Wishes from Gibe III Hydroelectric Project Staff

September marks the grand, gay and happy occasion in the lives of many Ethiopians. It is the classic New Year celebration which has great social, cultural and national value in Ethiopia celebrated on vast scale with much jest, joy and enthusiasm.

Read More ...

“...The Omo River is Now Becoming the Gorge of Development.”

Ambassador Teshome Toga, Speaker of the House of People’s Representatives (HPR) said Ethiopia is constructing the huge Gibe III Hydroelectric Project to make poverty a past history.

Read More ...

“All Ethiopians’ Ears and Eyes are on Gibe III Project”

On August 14-15, 2010, Abay Tsehay, the National Intelligence Advisor to the Prime Minister of the Federal Democratic Republic of Ethiopia along with Fikru Dessalegne, State Minister of Capacity Building and EEPCo’s Board Member, visited the activities of the project...

Read More ...

Reaction to Issues Raised by ‘South China Morning Post’ Concerning the Gibe III HEP

the sole reason that Ethiopia has shifted to China is that the international financiers have taken much more time in approving the fund ...

Read More ...

EEPCo signs accord with Chinese Company for Gibe III Project

The Ethiopian Electric Power Corporation (EEPCo) and Dongfang Electric Corporation (DEC), Chinese state-owned company, signed a company, signed a contractual agreement amounting to about USD 500 million ...

Read More ...

Distorted Facts Vs the Reality The Actual Picture of Gibe III Hydroelectric Project

Needless to say, many deliberate and irresponsible reports are being fabricated regarding the Gibe III Hydroelectric Project (HEP).   

Read More ...

Gibe III HEP Launches Satellite Office at Jinka Town

The Gibe III Hydroelectric Project (HEP) Office opened an Environmental and Social Impact Management and Mitigation Team branch office at Jinka town on Feb 2010.    

Read More ...

Office performs Public Consultations, Disclosure with Project-Affected Communities

the Gibe III Hydroelectric Project Office carried out a wide range public Consultations & disclosures and complimentary discussions with the upstream communities of the Project    

Read More ...

Consultants Reaffirm Gibe III HEP Viable in economic, financial, technical terms

the joint venture international consultants reaffirmed that the Gibe III Hydroelectric Project is considerably viable    

Read More ...

Gibe III Hydroelectric Project said Best Option in Power Sector Development

The African Development Bank (AfDB) and the Work Bank (WB) experts acknowledged Gibe III Hydroelectric Project is the best option in the power sector developments    

Read More ...

EEPCo, TBEA sign Contract for Gibe III-Wolaita substation Transmission Line Project

The EEPCo and TBEA, a Chinese company, singed a contractual agreement on July 24, 2009, amounting to Birr 380,883,690.99 (USD 34,007,472.41) for the installation of power transmision line from Gibe III Main station to the new Wolaita substation.    

Read More ...

Office Establishes Environmental Advisory Panel

The Gibe III Hydroelectric Project Office established Environmental Advisory Panel (EAP) in a bid to consult on the environmental issues during the implementation project.

Read More ...

EEPCo looks to win West African contract

Capita, (26 July 2009, Addis Ababa)-The Ethiopian Electric Power Corporation (EEPCo) recently participated in an international tender to manage the operation of the recently completed Bumbuna Hydroelectric Project (BHP) in Sierra Leone, which was constructed by Italian-based firm. Salini.

Read More ...

Kenya, Ethiopia to benefit from dam project

Kenya and Ethiopia are constructing a-multibillion hydroelectric project to benefit the two neigbouring countries, according to Kenyan officials.

Read More ...