EEPCo  |  Project Financer  |   Raised Issues  |  Public Consultation  |  Visitors   |  Organization Structure

Home
Brief
Progress
Gallery
Event
FAQ


Web Counter
  Hit Counter

BACKGROUND

The unprecedented socio-economic development of Ethiopia is becoming a vibrant pushing factor for the ever-increasing electric power demand. Since the demand for and the supply of electric energy is not growing in a corresponding manner, Ethiopian government has made extensive endeavors to alleviate the problem; and thereby has launched various hydroelectric power projects with some in their finishing phases like Tekeze (300MW), Gilgel Gibe II(420MW), Belese (460MW), Gibe III (1870MW),Fincha-Amerti-nesh (100MW) and some to start soon are Chemoga Yeda(280 MW), wind Project (120MW) and projects to start soon are Gibe IV (1472MW), Gibe V (560MW),and Halele-Werabesa(420 MW). Above all, utilization of the abundantly available water resource in generating electric power has given due emphasis. Being one of the monster hydropower projects with a generating capacity of 1,870MW, Gibe III Hydroelectric Project becomes a focus point for the government as well as the external donors.


GIBE III HYDROELECTRIC PROJECT

The objective of the project is to enhance the hydropower generation capacity of the country through developing a plant with a capacity of 1870 MW and with an annual energy production of 6,500 GWh, This in turn is expected to raise the present 800 MW installed capacity of the country by 234 percent.

Moreover, the project has the aim of ensuring exportation of power to the neighboring countries through regional Interconnection Transmission System so that Ethiopia will be in a place of gaining hard currency through sells of electricity.

Turnkey Contract Agreement adopted for the Gibe III Hydroelectric Project was issued by the Federation International Des Ingenieurs Conseils (FIDIC). The Agreement was signed between the Ethiopian Electric Power Corporation (EEPCo) and Salini Costruttori S.p.A of Italy (Contractor) on 19 th July 2006. Amendment was also made on the Contract Agreement on April 22, 2008 since changes happened to the scope of the work.

As far as the quality inspection is concerned, the quality control of the design and construction is carried out by a Joint Venture Consultant- ELC Electrocosult (Italy)& Coyne et Bellier(France) is hired by EEPCo as Employer representative.

Regarding the structure, the basic design of May 2006 foresaw a Rockfill Dam with a large spillway structure on the right bank and the power intakes, headrace tunnels, penstocks/manifolds, surge shafts, powerhouse, and switchyard on the left bank. However, due to difficulties with obtaining proper and sufficient insurance coverage for the Rockfill Dam, the dam has been changed to Roller Compacted Concrete (RCC).

The Gibe III hydroelectric Project which is anticipated to be completed on July 2013 has a construction cost of 1,470 Million Euro (20.7 Billion Ethiopian Birr).

LOCATION

The Gibe III Hydroelectric Project is located in the Southern Nations Nationalities & Peoples Regional State in Wolayta and Dawro Zones at about 470 km south west of Addis Ababa on the road via shashemene. It is situated along the lower course of the Omo River, some 155 km downstream of the Gilgel Gibe II Powerhouse.

GENERAL FEATURES OF THE PROJECT

The Gibe III Hydroelectric Project has the following major components:

Hydrology: The Gibe III catchment area is divided into two sections (monitored and unmonitored). The monitored section, approximately 66 percent of the total area, has 3 measurement stations and 40 years of flow records. The three stations are at;

a) The Gibe river near Abelti (the most important station)

b)Gojeb near Shebe, and

c) Wabi near Wolkitie. Run-off calculations made based on 40 years of reliable records.

For the section which is not monitored, approximately 33 percent of the total area, there are no direct measurements of flow available. Run-off is calculation made based on the rainfall data.

The catchment area for the project is 34,150 km2 with an average annual rainfall of 407mm. The average annual run-off estimated is 438 m3 /s and the total annual run-off is 13,876 million cubic meters .

Geology : The Gibe III Project site is located in the Jima volcanic formation, a thick succession of basalts and sialic rocks, divided into Jima Basalts and Jima Rhyolites. In the project area, the formation is constituted mainly by trachytes, basalts and pyroclastics.

Temporary and Permanent Facilities: Three temporary camps are provided on the right bank of the river, for the Employer/Employer's Representative staffs, the Contractor's expatriate staffs, and for the Workers. The Employer/Employer's Representative Camp includes accommodation, offices, canteen, laundry, and club. The Contractor's camp is similar but includes main clinic. The Contractor's offices are located elsewhere in a separate area on the right bank where other facilities such as the plant and equipment workshop, stores, and laboratory, are situated. The Workers' camp includes accommodation, canteens, clinic, and police station. Permanent camp will be constructeded on the left bank of the river.

Roads: The project includes construction of new permanent and temporary roads and rehabilitation of existing ones. The road from Welaita Sodo town to Bele via Chida town is a federal highway road which needs periodical rehabilitation .

Roller Compacted Concrete (RCC) Dam & Reservoir: The Roller Compacted Concrete Dam has a maximum height of 243 m and 610m of crest length. The dam will create a reservoir with total storage capacity of 14,700 million m3 (with live storage of 11,750 million m3 and dead storage of 2,950 million m3 ). The reservoir area covered by water is about 210 km 2 .

The dam has the following general features:

- crest level 896m

- total crest length 610m

- maximum flood level (PMF) 893m

- maximum/normal operating level 892m

- minimum operating level 800m

- overflow spillway level 873m

- overflow spillway length 108m

- maximum height above river bed 223m

- maximum height above foundation 243m

- basic triangle opening 0.75m

Diversion Tunnels: Two diversion tunnels of 13 m diameter and a smaller 7 m diameter diversion tunnel, located on the right bank of the river. The river diversion will be effected by a conventional layout of tunnels and cofferdams and is designed to pass a flood of 5,200m 3 /s, which is approximately a 30 years return period flood event.

Cofferdams: An upstream pre-cofferdam, upstream main cofferdam and a downstream cofferdam are envisaged. It will be useful to create a water head adequate to the large flow required to divert the water for the entire period of dam construction.

Power Tunnels: There are two power waterways comprising intakes, power tunnels, surge shafts, penstocks and manifolds, each branching into 5 turbine inlets are envisaged.

Powerhouse: A Powerhouse that is located at the toe of the dam on the left abutment, housing 10 Francis turbines with a power of 187 MW each for a total installed capacity of 1,870MW, 5 transformers are also installed at the back of the plant, converting the voltage from 15 kV to 400 kV.

Switch Yard: The switch yard is located on the left side of the river, on a plateau above the powerhouse at elevation of 1,010m above sea level equipped with a double bus bar scheme from where the five three-phase 400kV transmission lines start.

Spillway: A gated spillway is designed to pass:

o The design flood = 10,600 m 3 /s(10,000 years return period)

o The exceptional flood = 18,000m 3 /s(Probable Maximum Flood)

Electro- Mechanical: is one of the major undertaking activities subcontracted via International Competitive Bidding. The scope of work mainly comprises the design, supply, erection, site testing and commissioning and test running of 10 vertical type Francis type hydraulic turbines with their digital frequency governors and inlet valves, 10 vertical axis synchronous generators with a rating of 220MVA( rated power factor of 0.85 and 187MW) with their excitation systems. It also includes intake, powerhouse and switchyard protection, control and monitoring; telephone and communication, lifting, cooling, drainage, emergency diesel generators, ventilation and air conditioning, fire protection and compressed air supply systems, 15 mono-phase, 15kV/400kV step up transformers each one with 147MVA rating (441MVA, three phase rating to accommodate the outputs from two generating units) transformers.

Hydro Mechanical: is the other subcontracted activity that through International Competitive Bidding. The scope of work includes intake steel structures and gates, draft tube, middle level, diversion tunnel, spill way and ecological discharge gates with all their electro mechanical accessories. Steel linings for the penstocks and draft tubes and part of the surge shafts will also be undertaken. Spare parts and special tools will also be supplied by the subcontractor.

Transmission Lines: The power generated at Gibe III will be transmitted with two double circuit tower transmission lines. Line 1 has a length of 50.3km and it carries double three phase circuits at 400kV from Gibe III switchyard to Wolyta Sodo substation. Line 2 has a length of 51km and it carries single three phase circuit at 400kV from Gibe III switchyard to Wolyta Sodo substation. The Contractor who undertakes the design and construction of the transmission lines is a private company called TBEA from China. The Contract price is 34,007, 472.41USD, of which 85 percent is to be paid in foreign currency. The financing is facilitated by the Contractor using supplier's credit scheme from the EXIM Bank of China. The local component of the transmission line's project cost will be covered by the Ethiopian Electric Power Corporation (EEPCo)

Project Layout 







 

Copyright © 2009 Gibe3 Hydroelectric Project

News and Events



"Gibe III won’t affect Kenya: Ambassador"

The Ethiopian Herald on its issue on December 16, 2011 posted an interview with The Kenyan Ambassador in Ethiopia Dr. Monica Juma.

Read More ...

"Life is better with Trees"
Tree Planting Day around Gibe III Project (July 24, 2011)

As part of promoting environmental protection, the Environmental and Social Monitoring and
Management Sub-Process team of EEPCo in collaboration with the Health, Safety and
Environment (HSE) section of the EPC contractor and the camp manager, organized a tree
planting occasion on July 24, 2011.

Read More ...

Launch: RCC Dam Concreting
Works

The Gibe III Hydroelectric Project's Site Office
announced that the Dental Concreting work of
the Roller Compacted Concrete (RCC) Dam
foundation, has been officially commenced on
August 19, 2011.

Read More ...

Pastoral community Representatives Visit to GibeIII Dam Construction Site

Lokomori Lotolien, 43, of Dassenech ethic groups seems to scrutinize things restlessly as he is responsible to convey all the information he gathered about Gibe III Dam construction, and the other operational Dams (Gilgel Gibe I and II) to the community who delegates him to investigate the impacts of those Dam on flows of the Omo River.

Read More ...

“We had great enthusiasm to visit this giant Project “

Luckily, the Gibe III Hydroelectric Project has called the attention of many visitors since its infant stage. From the high level government officials to various academic and media institutions have paid attentive visits frequently.

Read More ...

A Report of the ESAP (Environmental and Social Advisory Panel) of Gibe III Hydroelectric Project on First Site Visit

The Gibe III Hydroelectric Project is now under construction phase when operational it is expected to produce 1870 MW. Currently Salini COSTRUTTORI S.p.A on behalf of EEPCo is undertaking construction of this project.

Read More ...

Gibe III Today (News Letter 2)

High-ranking government officials expressed their impression regarding the progress of work on the Gibe III Hydroelectric Project and the united efforts of its staff.

Read More ...

Gibe III Today (News Letter 1)

The African De v e l o pme n t Bank (AfDB) and the World Bank (WB) experts acknowledged Gibe III h y d roe l e c t r i c project is the best option in the power sector developments, and would boost the economic and social integrations among the Eastern African countries

Read More ...

GIBE DAM III - Pride of Ethiopia!

Gibe Dam III is indeed the Pride of Ethiopia! Once completed this project will generate 1870 Mega Watt electric power. Currently Ethiopia has only ~ 800 Mega Watt and Gibe III will boost the output by 230%! This project provides thousands of job opportunities for the local communities.

Read More ...

Letter to the Editor By Azeb Asnake, Gibe III Hydroelectric Project Manager1

We appreciate for her “Greens must have very hard hearts if they can look at flood-hit Ethiopia and still say ‘don’t build dams” article posted on www.spiked-online.com. Rothschild has exactly reflected the facts of the Gibe III Hydroelectric Project. Thank you, Rothschild.

Read More ...

Ethiopia - They don’t give a dam about development Greens must have very hard hearts if they can look at flood-hit Ethiopia and still say ‘don’t build dams’.

Recently a group of international NGOs has been leading a campaign to stop the building of the Gibe III hydroelectric dam in Ethiopia. They say the dam will disrupt the local ecosystem and the traditional ...

Read More ...

2003 E.C . New Year Best Wishes from Gibe III Hydroelectric Project Staff

September marks the grand, gay and happy occasion in the lives of many Ethiopians. It is the classic New Year celebration which has great social, cultural and national value in Ethiopia celebrated on vast scale with much jest, joy and enthusiasm.

Read More ...

“...The Omo River is Now Becoming the Gorge of Development.”

Ambassador Teshome Toga, Speaker of the House of People’s Representatives (HPR) said Ethiopia is constructing the huge Gibe III Hydroelectric Project to make poverty a past history.

Read More ...

“All Ethiopians’ Ears and Eyes are on Gibe III Project”

On August 14-15, 2010, Abay Tsehay, the National Intelligence Advisor to the Prime Minister of the Federal Democratic Republic of Ethiopia along with Fikru Dessalegne, State Minister of Capacity Building and EEPCo’s Board Member, visited the activities of the project...

Read More ...

Reaction to Issues Raised by ‘South China Morning Post’ Concerning the Gibe III HEP

the sole reason that Ethiopia has shifted to China is that the international financiers have taken much more time in approving the fund ...

Read More ...

EEPCo signs accord with Chinese Company for Gibe III Project

The Ethiopian Electric Power Corporation (EEPCo) and Dongfang Electric Corporation (DEC), Chinese state-owned company, signed a company, signed a contractual agreement amounting to about USD 500 million ...

Read More ...

Distorted Facts Vs the Reality The Actual Picture of Gibe III Hydroelectric Project

Needless to say, many deliberate and irresponsible reports are being fabricated regarding the Gibe III Hydroelectric Project (HEP).   

Read More ...

Gibe III HEP Launches Satellite Office at Jinka Town

The Gibe III Hydroelectric Project (HEP) Office opened an Environmental and Social Impact Management and Mitigation Team branch office at Jinka town on Feb 2010.    

Read More ...

Office performs Public Consultations, Disclosure with Project-Affected Communities

the Gibe III Hydroelectric Project Office carried out a wide range public Consultations & disclosures and complimentary discussions with the upstream communities of the Project    

Read More ...

Consultants Reaffirm Gibe III HEP Viable in economic, financial, technical terms

the joint venture international consultants reaffirmed that the Gibe III Hydroelectric Project is considerably viable    

Read More ...

Gibe III Hydroelectric Project said Best Option in Power Sector Development

The African Development Bank (AfDB) and the Work Bank (WB) experts acknowledged Gibe III Hydroelectric Project is the best option in the power sector developments    

Read More ...

EEPCo, TBEA sign Contract for Gibe III-Wolaita substation Transmission Line Project

The EEPCo and TBEA, a Chinese company, singed a contractual agreement on July 24, 2009, amounting to Birr 380,883,690.99 (USD 34,007,472.41) for the installation of power transmision line from Gibe III Main station to the new Wolaita substation.    

Read More ...

Office Establishes Environmental Advisory Panel

The Gibe III Hydroelectric Project Office established Environmental Advisory Panel (EAP) in a bid to consult on the environmental issues during the implementation project.

Read More ...

EEPCo looks to win West African contract

Capita, (26 July 2009, Addis Ababa)-The Ethiopian Electric Power Corporation (EEPCo) recently participated in an international tender to manage the operation of the recently completed Bumbuna Hydroelectric Project (BHP) in Sierra Leone, which was constructed by Italian-based firm. Salini.

Read More ...

Kenya, Ethiopia to benefit from dam project

Kenya and Ethiopia are constructing a-multibillion hydroelectric project to benefit the two neigbouring countries, according to Kenyan officials.

Read More ...