EEPCo  |  Project Financer  |   Raised Issues  |  Public Consultation  |  Visitors   |  Organization Structure

Home
Brief
Progress
Gallery
Event
FAQ


Web Counter
  Hit Counter

Project Financing

The construction cost of Gibe III Hydroelectric Project is 1,470 million Euro. Ethiopian government is the sole financer with the local currency amounting to 448 million Euro payable in Birr, and in addition to the local payments,it has paid so far 164 million Euros in foreign currency to the contractor.

A contractual agreement of 35 million Euro has already been signed between Ethiopian Electric Power Corporation(EEPCo) and TBEA Limited company of China for the installation of power transmission lines from Gibe III to Wolayta Sodo substation. Of which, 85 percent is to be covered by the EXIM Bank of Chinese government.

The electro-mechanical (EM) cost, about 250 million, of the projects is expected to be covered by the African Development Bank (AfDB), and the European Investment Bank (EIB) is as well expected to finance nearly 100 million Euros for the equipment supply & installation of the hydro- mechanical (HM) part of the project.

The detailed financial status is indicated Below:

The Government of Ethiopia (GoE)

Ethiopian government is the main source of finance to the project through EEPCo as equity. The GoE will finance the local currency portion of the Project's cost, which is equivalent to 448 million Euros. It is also expected to finance the foreign currency balance.

 

African Development Bank
(Public Window)

 Ethiopian government has requested the African Development Bank about 250 million Euro to cover the electro-mechanical cost of the project.

 The Bank's several missions had been here in Ethiopia to hold various meetings with the Ministry of Mines and Energy (MoME), EEPCo`s various offices and institutions including the Ethiopian Environmental Protection Authority, key NGOs, the Bank`s Country Office. During the occasion, EEPCo signed an Aide memoire with the respective missions.

 All the final environmental and social impact assessment (ESIA) and resetlment action plan (RAP) reports are submitted to AfDB and then the Bank has posted the executive summaries of the reports on it's web site, but no comments had been received until its deadline.

 During the 44th African Development Bank Annual Meeting, the issue of Gibe III has been raised and discussed among donors and NGOs. The detail information was given on a separate report.

In addition,  a consultative meeting with Kenyan government delegations has been conducted on June 3, 2009, in which EEPCo and its consultants presented about ESIA issues of the project to the delegation. The meeting was organized by the Ministry of Foreign Affairs (MoFA), Ministry of Water Resources (MoWR) and EEPCo.

The high level delegation led by John Rao Nyaoro, Kenyan director of water resource, also visited the Gilgel.Gibe I, II and III project sites from June 4-6, 2009.

 On March 17, 2009, the Board of Directors paid a visit to the project site and the Project Concept Note has been presented to the Bank's senior management for approval. To this end, EEPCo has provided the necessary information.

Although the project Concept Note is planned to be presented to the Bank's Board of Directors in September 2009, the Bank seems to wait the Economic, Financial and Technical assessment ( EFTA) of the independent consultant results, and hence currently mediation is on progress with the Friends of Lake Turkana (FoLT).

African Development Bank
(Private Window)

P1080497 The Bank's Private Window has shown interest to finance up to 100 million Euro for the Project. An Aide Memoire has been signed with the general agreement of establishing a Special Purpose Vehicle (SPV).

 

 Recruitment of Financial Advisor and negotiation have been progressing since June 10, 2009.

European Investment Bank (EIB)

 The Ethiopian Government has requested the European Investment Bank about 100 Million Euros to finance the hydro-mechanical part of the project.

The Bank's  several missions had been here in Ethiopia; in due time, they visited Gibe II and Gibe III Projects followed by thorough discussions with EEPCo's management staff.

 The hydro-mechanical steel structures tender document was given to the Bank for approval. The tender evaluation report has also been submitted to the Bank for endorsement. According to the evaluation report, the bidders are found to be technically acceptable and the economical advantageous offer has been selected. EIB's "No Objection" on the HSS Bid Evaluation Report has been received on 9 January 2009. EIB has advised to conduct contract negotiation.

 EIB's mission came to Addis Ababa and discussed about the additional studies required to fill the gap on the Gibe III ESIA studies.

Italian Government

2008-09-05 114 A formal request for financing of Gibe III Project has been sent to the Italian government by the Prime Minister's Office. Hence, the government of Italy is anticipated to finance about 250 Million Euro so as to cover part of the civil work costs of the project.

 A high level delegation paid a visit to the project site on September 2008. Following presentations by EEPCo about the project, there were discussions with H.E, Minister of Mines and Energy. Upon the request of the high level mission,all the Environmental and Social Impact Assessment (ESIA) reports were submitted to the Italian government through the Ministry of Foreign Affairs. 

 On April 22, 2009, another high level delegation visited the project site . As per the remarks made by the delegation, additional and updated documents were sent to the Italian government through the Ministry of Foreign Affairs.

 In addition, the high level government delegation had been to Ethiopia in mid June 2009 to visit the Gilgel Gibe II Project. During the visit, the delegation has confirmed its government's commitment to finance Gibe III Project. Additional documents required for project appraisal were sent to the government of Italy (Director General for Development cooperation).

Chinese Government

The Chinese government is the main financier for the installation of power transmission line  from Gibe III main station  to the new Wolaita substation. The Ethiopian Electric Power Corporation (EEPCo) and TBEA, a Chinese company, singed a contractual agreement on July 24, 2009, amounting to USD 34,007,472.41. Of which, 85 percent will be covered by Chinese government through EXIM Bank.

The installation of the power grid comprises LINE 1 & LINE 2 covering 50.3km and 51km, respectively. The first line has 400kv, 3-phases, double circuit conductor on a double circuit transmission line while the second one, having identical features to Line 1,  consists of single circuit conductor with the same transmission line and kilo volts.







 

Copyright © 2009 Gibe3 Hydroelectric Project

News and Events



"Gibe III won’t affect Kenya: Ambassador"

The Ethiopian Herald on its issue on December 16, 2011 posted an interview with The Kenyan Ambassador in Ethiopia Dr. Monica Juma.

Read More ...

"Life is better with Trees"
Tree Planting Day around Gibe III Project (July 24, 2011)

As part of promoting environmental protection, the Environmental and Social Monitoring and
Management Sub-Process team of EEPCo in collaboration with the Health, Safety and
Environment (HSE) section of the EPC contractor and the camp manager, organized a tree
planting occasion on July 24, 2011.

Read More ...

Launch: RCC Dam Concreting
Works

The Gibe III Hydroelectric Project's Site Office
announced that the Dental Concreting work of
the Roller Compacted Concrete (RCC) Dam
foundation, has been officially commenced on
August 19, 2011.

Read More ...

Pastoral community Representatives Visit to GibeIII Dam Construction Site

Lokomori Lotolien, 43, of Dassenech ethic groups seems to scrutinize things restlessly as he is responsible to convey all the information he gathered about Gibe III Dam construction, and the other operational Dams (Gilgel Gibe I and II) to the community who delegates him to investigate the impacts of those Dam on flows of the Omo River.

Read More ...

“We had great enthusiasm to visit this giant Project “

Luckily, the Gibe III Hydroelectric Project has called the attention of many visitors since its infant stage. From the high level government officials to various academic and media institutions have paid attentive visits frequently.

Read More ...

A Report of the ESAP (Environmental and Social Advisory Panel) of Gibe III Hydroelectric Project on First Site Visit

The Gibe III Hydroelectric Project is now under construction phase when operational it is expected to produce 1870 MW. Currently Salini COSTRUTTORI S.p.A on behalf of EEPCo is undertaking construction of this project.

Read More ...

Gibe III Today (News Letter 2)

High-ranking government officials expressed their impression regarding the progress of work on the Gibe III Hydroelectric Project and the united efforts of its staff.

Read More ...

Gibe III Today (News Letter 1)

The African De v e l o pme n t Bank (AfDB) and the World Bank (WB) experts acknowledged Gibe III h y d roe l e c t r i c project is the best option in the power sector developments, and would boost the economic and social integrations among the Eastern African countries

Read More ...

GIBE DAM III - Pride of Ethiopia!

Gibe Dam III is indeed the Pride of Ethiopia! Once completed this project will generate 1870 Mega Watt electric power. Currently Ethiopia has only ~ 800 Mega Watt and Gibe III will boost the output by 230%! This project provides thousands of job opportunities for the local communities.

Read More ...

Letter to the Editor By Azeb Asnake, Gibe III Hydroelectric Project Manager1

We appreciate for her “Greens must have very hard hearts if they can look at flood-hit Ethiopia and still say ‘don’t build dams” article posted on www.spiked-online.com. Rothschild has exactly reflected the facts of the Gibe III Hydroelectric Project. Thank you, Rothschild.

Read More ...

Ethiopia - They don’t give a dam about development Greens must have very hard hearts if they can look at flood-hit Ethiopia and still say ‘don’t build dams’.

Recently a group of international NGOs has been leading a campaign to stop the building of the Gibe III hydroelectric dam in Ethiopia. They say the dam will disrupt the local ecosystem and the traditional ...

Read More ...

2003 E.C . New Year Best Wishes from Gibe III Hydroelectric Project Staff

September marks the grand, gay and happy occasion in the lives of many Ethiopians. It is the classic New Year celebration which has great social, cultural and national value in Ethiopia celebrated on vast scale with much jest, joy and enthusiasm.

Read More ...

“...The Omo River is Now Becoming the Gorge of Development.”

Ambassador Teshome Toga, Speaker of the House of People’s Representatives (HPR) said Ethiopia is constructing the huge Gibe III Hydroelectric Project to make poverty a past history.

Read More ...

“All Ethiopians’ Ears and Eyes are on Gibe III Project”

On August 14-15, 2010, Abay Tsehay, the National Intelligence Advisor to the Prime Minister of the Federal Democratic Republic of Ethiopia along with Fikru Dessalegne, State Minister of Capacity Building and EEPCo’s Board Member, visited the activities of the project...

Read More ...

Reaction to Issues Raised by ‘South China Morning Post’ Concerning the Gibe III HEP

the sole reason that Ethiopia has shifted to China is that the international financiers have taken much more time in approving the fund ...

Read More ...

EEPCo signs accord with Chinese Company for Gibe III Project

The Ethiopian Electric Power Corporation (EEPCo) and Dongfang Electric Corporation (DEC), Chinese state-owned company, signed a company, signed a contractual agreement amounting to about USD 500 million ...

Read More ...

Distorted Facts Vs the Reality The Actual Picture of Gibe III Hydroelectric Project

Needless to say, many deliberate and irresponsible reports are being fabricated regarding the Gibe III Hydroelectric Project (HEP).   

Read More ...

Gibe III HEP Launches Satellite Office at Jinka Town

The Gibe III Hydroelectric Project (HEP) Office opened an Environmental and Social Impact Management and Mitigation Team branch office at Jinka town on Feb 2010.    

Read More ...

Office performs Public Consultations, Disclosure with Project-Affected Communities

the Gibe III Hydroelectric Project Office carried out a wide range public Consultations & disclosures and complimentary discussions with the upstream communities of the Project    

Read More ...

Consultants Reaffirm Gibe III HEP Viable in economic, financial, technical terms

the joint venture international consultants reaffirmed that the Gibe III Hydroelectric Project is considerably viable    

Read More ...

Gibe III Hydroelectric Project said Best Option in Power Sector Development

The African Development Bank (AfDB) and the Work Bank (WB) experts acknowledged Gibe III Hydroelectric Project is the best option in the power sector developments    

Read More ...

EEPCo, TBEA sign Contract for Gibe III-Wolaita substation Transmission Line Project

The EEPCo and TBEA, a Chinese company, singed a contractual agreement on July 24, 2009, amounting to Birr 380,883,690.99 (USD 34,007,472.41) for the installation of power transmision line from Gibe III Main station to the new Wolaita substation.    

Read More ...

Office Establishes Environmental Advisory Panel

The Gibe III Hydroelectric Project Office established Environmental Advisory Panel (EAP) in a bid to consult on the environmental issues during the implementation project.

Read More ...

EEPCo looks to win West African contract

Capita, (26 July 2009, Addis Ababa)-The Ethiopian Electric Power Corporation (EEPCo) recently participated in an international tender to manage the operation of the recently completed Bumbuna Hydroelectric Project (BHP) in Sierra Leone, which was constructed by Italian-based firm. Salini.

Read More ...

Kenya, Ethiopia to benefit from dam project

Kenya and Ethiopia are constructing a-multibillion hydroelectric project to benefit the two neigbouring countries, according to Kenyan officials.

Read More ...